Late October Group Buy Updates

Southpaw 65+ 

All plates inclusive of bent plates are done and are ready to be shipped to the US and EU which should happen at the end of this week or early next week. The CNC work for the aluminum cases were finished last week, but some  had issues with tolerances which will be addressed this week. The factory that is handling these has a backlog of things that need to be hand-finished so it's going to be a week or so before these move onto the hand finishing stage. After that, those are off to sandblasting and anodizing. 

 

Lunar AEK 65

All parts have been made, hand finished, and sandblasted. They'll be coming back from anodizing this week. PCB fabrication started last week and should wrap up at the end of this month if there are no issues with sourcing components. 

 

Southpaw FS

Acrylic plates have been cut and have arrived but the wrong files were sent to the fab. These will be recut which should not take long. The old acrylic plates have the reset cutout off center and the left shift missing the ISO spec cutout so those will be sold later on as b-stock on the website. The aluminum and brass plates haven't been cut yet (thankfully) so the new files will be sent to manu and those will be made later this month. The cases are still awaiting hand finishing which should be started sometime this week or next week. 

 

Kit and Parts Restock

We will be stocking some GMK screw in stabilizers towards the end of this month or the beginning of next month.